THE EDMONSON VOICE
  • Home
  • News
  • Community
    • VOICE Calendar >
      • About VOICE Calendar
    • County Schools Calendar
  • Obits
  • Sports
    • WildcatsLive/Schedules
    • Recorded Game Videos
  • Weather
  • Features
    • Opinion
    • Ask Mongoose
    • Legal/Professional Policy
    • Our Staff
    • Contest Rules
    • Our Sponsors
  • FAQs
Picture
Picture
Picture

Edmonson County's Number One Source for Local News

Still No Specific Timeline For Sunfish-Roundhill Road Rebuild, But Judge/Exec Says it is Priority

5/6/2025

0 Comments

 
Picture
Site of the Sunfish-Round Hill Road breach, May 6, 2025.
Darren Doyle, story and photos:
After three years, the specific timeline for the rebuild of Sunfish-Round Hill Road remains unknown as Edmonson County Judge/Executive Scott Lindsey says "complexity of the work," and things "factored in that we were not accounting for," are some of the issues the county is facing with the massive road project.

The county road off of HWY 70 (Morgantown Road) and HWY 187 (Sunfish Road) first began to collapse in the summer of 2022 due to the parallel Cub Creek that had exceed its original banks and began eroding the base of the road. The initial extensive repair was attempted by the Edmonson County Road Department, under the direction of then supervisor Greg Carroll, hired by the fiscal court led by former Judge/Executive Wil Cannon.

According to the current Judge/Executive's Office during a March 2024 interview, the more the road crew worked on the repair, the more repairs were needed. Eventually, the entire base of the road failed and was dug completely down to the creek, at a depth of nearly 20 feet from the top of the road. This is when Judge Lindsey said the county discovered that they didn't have the funds to rebuild the road. As a result, portable barriers with "Road Closed" signage were placed on both sides of the breach.

However, in April of 2023, Donald Hardison, a Muhlenberg County man, was found deceased in a 2007 Ford Expedition after driving off the closed road into water at the construction site of Sunfish-Round Hill Road. It is unclear whether or not the barriers were in place when the man drove into the water. At the time, Judge Lindsey said they had been placed in the correct areas but it was not known where they were at the time of the accident or if the man simply avoided and driven around them. It is an approximately 20 foot drop off from the roadway to the bottom.

Regardless of where they are placed, the barriers alone can still be driven around fairly easily. In December of 2019, Alexandra Richardson was able to drive around the same barricade on Oak Hill Road, where flooding had caused the water to be several feet over the road. She drove into the water while intoxicated with her 20 month-old son and another juvenile. The boy died as a result of the crash and Richardson was charged and convicted of murder and sentenced to 20 years in jail.
Picture
View of what used to be the roadway on Sunfish-Round Hill Road, May 6, 2025.
Picture
Nearly three weeks passed after Mr. Hardison's accident before Edmonson County Fiscal Court voted to take a more permanent action to avoid the possibility of anyone else driving into the drop off. Some Sunfish residents attended the May 8, 2023 fiscal court meeting and demanded action be taken immediately. The court voted that day to place large loads of rock at both breaches which still remain today, along with "Road Closed" signs.

The breach is well over 100 foot long by 20 foot deep, and still has a portion of Cub Creek running into the original base.

Judge Lindsey announced to the Edmonson County Fiscal Court on March 18, 2024, that he had found a possible solution for funding, which was estimated to cost around $900K. He said that while the Federal Emergency Management Agency (FEMA) had agreed to pay for the project, the county would have to cover the initial cost, which they didn't have. Lindsey said that the county could secure a line of credit through the Kentucky Association of Counties, a state governing body of county offices in KY, (KACo). He also said that he hoped the work would be done in 2024, which did not happen.

We followed up with Judge Lindsey last week about the status of the project that has disrupted the lives of many Sunfish area residents, and asked for an update.

The credit line was secured in June of 2024, according to Judge Lindsey and the $900k has been borrowed. The funds have been placed in a separate account, ready for use.

Lindsey said a variety of factors have hindered the project but that he feels they have all been addressed and the county is close to moving forward.

"Some of the factors that took some time to complete were having to do with the geo-studies that were completed in and around the roadbed to make sure that the foundation the road was being rebuilt on was strong enough to support the road," he said. "Or does it need to be secured by using engineering methods like rail and cribbing that would add strength to the affected area. There were several other tests that were done as well."


Picture
Second barrier of rock past the "Road Closed" sign.
He also said due to the water issue from the creek, rerouting the water under the road without eroding the road base had to be part of the solution. If not, the road would continue to fail as a result of the same issue.

"There were also multiple options presented as to the possible placement of the road based on the information gained from the results of the engineering studies. Once the best option was chosen, we had to obtain the right-of-ways and permissions to use that model from the landowner. That has now been discussed and verbally agreed to, and we are moving forward using that information."

Lindsey said he had hoped the entire project could have been completed last year.

"Unfortunately, due to the complexity of the work, and things that factored in that we were not accounting for originally, the project hasn't moved forward as quickly as we had hoped or intended."

He said the county hired an engineering firm, Arnold Consulting Engineering Services, (ACES) who was an approved state vendor, and one that the county has used for other projects in the past.

"They have been doing the testing and engineering for the blueprints and planning to rebuild the road. They are handling the engineering and scope of work for the project. We will take sealed bids for the reconstruction once ACES gets the bid packet finalized."

Judge Lindsey said while no specific time period has been discussed by ACES, he said it is a priority and they are working on that now. Once they submit all the information to the county, the fiscal court will advertise for bids, which would take two to three weeks, then those bids will be opened and read at the following meeting.

"It is the goal of all involved to be able to get this project completed this year," Judge Lindsey said. "We want to get it completed as soon as possible."
Picture
0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    COMMENTING/LEGAL
    Deadline INFO
    Picture
    Picture
    Picture

    Archives

    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014

COPYRIGHT 2014-2025.
HOME
NEWS 
COMMUNITY


OBITS
FEATURES
WEATHER
​​
WILDCATS LIVE
​
SPORTS
CONTACT
Copyright 2014-2025 The Edmonson Voice.
​The Edmonson Voice logos are registered trademarks.
Call or text: 270-597-6550 ​[email protected]
PO BOX 94
BROWNSVILLE, KY 42210
CLICK HERE FOR DEADLINE INFO

  • Home
  • News
  • Community
    • VOICE Calendar >
      • About VOICE Calendar
    • County Schools Calendar
  • Obits
  • Sports
    • WildcatsLive/Schedules
    • Recorded Game Videos
  • Weather
  • Features
    • Opinion
    • Ask Mongoose
    • Legal/Professional Policy
    • Our Staff
    • Contest Rules
    • Our Sponsors
  • FAQs